Upcoming Construction: I-205 Path, SW Sheridan, SE 22nd, NE Cesar Chavez, and Riverview Cemetery (UPDATED)

There are more than a couple street and trail closures coming up in March & April so we’ve rounded up the last information here, all in one place. Find out where and when to expect delays and closures, and be sure to follow @PDXBikeTraffic to stay up to date with the latest information impacting your commute!

I-205 Path near Airport Way, until mid-June (Map)

“From mid-March to mid-June 2013, bicyclists and pedestrians using the I-205 multi-use path will experience occasional delays during the week while the contractor does pile driving and other work using large cranes next to the path. Flaggers will close the trail for up to 20 minutes at a time throughout the day.”

Riverview Cemetery, March 13 & 14
Riverview Cemetery will be closed dusk through dawn on the 13th & 14th during blasting work for the Sellwood Bridge:

“Blasting is scheduled on March 13 and 14 as part of the work to widen Highway 43 for the new bridge interchange. On blast nights, intermittent closures of traffic lanes and the highway and bridge will happen between 7 pm and 5 am. Highway and bridge closures will last from 5 to 20 minutes for each blast. Five minutes and one minute before each blast, a warning siren will sound. The siren will probably be louder than the blast itself. Two or three blasts are scheduled each night between 9 pm and 3 am. Travelers can avoid delays by choosing alternate routes on blast nights.”

NE Cesar Chavez between NE Senate & NE Wasco, March 14 – 18 (Map)

“(PORTLAND, Ore.) – The City of Portland Bureau of Transportation advises the traveling public that street improvements will require a lane closure on Northeast Cesar Chavez Boulevard between Northeast Senate Street and Northeast Wasco Street beginning Thursday, March 14, through Monday, March 18, all hours and all days. The public is advised to expect delays, travel cautiously, observe all lane closures and directions by flaggers, and use alternate routes if possible.

The southbound right lane (curb lane) will be closed all hours and all days for this project with the southbound left lane open. Northbound traffic will be unaffected. The lane closure is necessary to remove and replace both the base and the surface layers of an isolated section of the road to stabilize the foundation of the road and prevent potholes and other surface distress.

Local access to residences and businesses will be provided.

This work is weather-dependent, and the schedule may change.”

SW Sheridan between SW Barbur and SW 5th, March 19 – 22 (Map)

“(PORTLAND, Ore.) – The City of Portland Bureau of Transportation advises the traveling public that street improvements will require lane closures on Southwest Sheridan Street between Southwest Barbur Boulevard and Southwest Fifth Avenue beginning Tuesday, March 19, through Friday, March 22, from 7 a.m. to 5 p.m. weekdays. The public is advised to expect delays, travel cautiously, observe all lane closures and directions by flaggers, and use alternate routes if possible.

Two lanes will remain open at all times. The lane closures are necessary to grind down the existing pavement and repave 0.23 lane miles of the street.

Local access to residences and businesses will be provided.

This work is weather-dependent, and the schedule may change.”

SW 5th between SW Broadway & SW Sheridan, March 25 – 28
(Map)

“(PORTLAND, Ore.) – The City of Portland Bureau of Transportation advises the traveling public that street improvements will require lane closures on Southwest Fifth Avenue between Southwest Broadway and Southwest Sheridan Street beginning Monday, March 25, through Thursday, March 28, from 7 a.m. to 5 p.m. weekdays. The public is advised to expect delays, travel cautiously, observe all lane closures and directions by flaggers, and use alternate routes if possible.

Two lanes will remain open at all times. Local access to residences and businesses will be provided. The lane closures are necessary to grind down the existing pavement and repave 0.4 lane miles of the street.

In addition to paving the street, permanent new striping will change the lane configurations on SW Barbur Blvd., SW Sheridan St. and SW Fifth Ave. Both SW Fifth Ave. and SW Sheridan St.will have three travel lanes plus one buffered bike lane that provides an important bikeway connection between Downtown Portland and SW Barbur Blvd. The lane changes also create an opportunity for buffered bike lanes on Barbur and a wider sidewalk on the east side of Barbur in the future. See before and after maps.

This work is weather-dependent, and the schedule may change.”

SE 22nd between SE Powell & SE Lafayette, March 25 – April 8 (Map)

“(PORTLAND, Ore.) – The City of Portland Bureau of Transportation advises the traveling public that street improvements will require a northbound lane closure on Southeast 22nd Avenue between Southeast Powell Boulevard and Southeast Lafayette Street beginning Monday, March 25, through Monday, April 8, all hours and all days. The public is advised to expect delays, travel cautiously, observe all lane closures and directions by flaggers, and use alternate routes if possible.

The lane closure is necessary to remove and replace both the base and the surface layers of isolated sections of the road to stabilize the foundation of the road and prevent potholes and other surface distress.

A detour will be in effect to accomplish this work. Northbound traffic on SE 22nd Avenue will be detoured onto SE Lafayette Street, west to SE 21st Avenue, then north to SE Powell Boulevard.

Local access to residences and businesses will be provided. Sidewalks will be kept open.

This work is weather-dependent, and the schedule may change.”